Tools

Small models you can push around. Change an input, watch the result, and build the intuition before you need it in a budget meeting.

Unit economics

Move churn, margin and CAC to see LTV, LTV:CAC and payback respond.

Read the lesson →

Lifetime value

$800

LTV : CAC

1.3×

CAC payback

15.0 mo

Customer lifetime

20 mo

Below the usual bar of LTV ≥ 3× CAC with payback inside 12 months. Try halving churn and watch LTV double.

Break-even

Find the volume where contribution margin covers fixed costs.

Read the lesson →

Contribution margin

$400

Break-even units

150

Monthly profit

−$12,000

CM ratio

80%

Green is revenue, red is total cost, and the dot is break-even. The dashed line is your current volume: left of the dot you lose money, right of it each unit adds its full contribution margin to profit.

NPV & payback

Discount a project's cash flows and test what a late start does to it.

Read the lesson →

Net present value

$23,291

Undiscounted ROI

30%

Payback

2.3 yr

PV of benefits

$323,291

Now
−$300,000
Yr 1
$118,182
Yr 2
$107,438
Yr 3
$97,671

Each bar is a cash flow in today's dollars. Push the start date out a year or raise the discount rate and watch a project that looked comfortable turn negative.

Team cost

What a team really costs per year, per sprint and per meeting.

Read the lesson →

Annual team cost

$1,248,000

Per two-week sprint

$48,000

Per engineer-hour

$116

One-hour all-team meeting

$693

Fully loaded cost is base salary times the load factor; the hourly figure assumes about 1,800 working hours a year. Use the sprint number when someone asks for “a quick two-week project”.

Communication paths

Watch coordination grow with the square of team size.

Read the lesson →

Communication paths

15

Paths per person

2.5

Paths follow n(n − 1) ÷ 2. Going from 6 people to 12 doubles the hands and more than quadruples the paths (15 → 66).

Cost of delay

Sequence two projects by CD3 and price the difference.

Read the lesson →

CD3 of A

5,000

CD3 of B

7,500

Delay cost, A first

$470,000

Delay cost, B first

$430,000

Do B first: the order with the higher CD3 saves $40,000 in value lost while waiting. One team, one project at a time; each project loses its weekly value for every week until it ships.

Conversion funnel

See how each stage's conversion rate multiplies into customers and revenue.

Read the lesson →

New customers / month

20

New MRR / month

$1,000

Overall conversion

0.20%

Visitors per customer

500

Visitors
10,000
Sign-ups
500
Activated
200
Paying
20

Output is volume times every rate, so a gain at any stage multiplies through. Compare doubling traffic with lifting activation by half: the second is usually cheaper.

Error budget

Turn an availability target into minutes of downtime you can spend.

Read the lesson →

Budget per 30 days

43.2 min

Budget per year

8.8 h

Remaining this month

23.2 min

Budget used

46%

Budget remains: keep shipping. Each extra nine divides the allowance by ten, and costs far more to achieve than the last.